1. Project Title:

construction eight berths - up (Link span)

2. Project Description and technical specifications:

In order to achieve the comprehensive plan policies island and on the creation of infrastructure facilities to import 3 million tourists in Horizons Master Plan, Kish Free Zone Organization considering 8 berths mechanized (Link span) on the astern arm of the island’s harbor foreshore. The docks will be capable of berthing of the barge and landing 500 tons to

3. Location:

Kish commercial seaport

4. The volume of project construction operations:

NumberEquipment
   120.000Cubic metersEarthworks
  950tonsSteel Works
  2300Cubic metersConcreting operations
  1170tonsPiling operations

5. Physical progress of the project:
Technical studies have been conducted and the draft contract prepared by a -3 factor is ready to exchange with contractors
6. Timing of the project:

: Estimated project duration is 24 months.
7. Estimated project cost:

The cost of the project is estimated around 440 billion Rials.
8. Ways to repay debts:

Liabilities resulting from financing the purchase is repaid by real estate.
9. To provide guarantees for the financing:

Kish Free Zone Organization guarantees the repayment of debt principal and interest. To provide guarantees for the financing: Kish Free Zone Organization guarantees the repayment of debt principal and interest